Travels with Jim follows Jim Huston around the country as he visits with landscapers and helps them understand their numbers to make smarter decisions.
He had a good handle on the production side of his business, but he had no idea how to handle the budgeting and pricing side of it. In desperation, he signed up for an estimating workshop where he hoped that he would learn how to address these issues.
Faulty math assumptions.
At the workshop, Bill learned the MORS (multiple overhead recovery
- Materials should be marked up 10 percent for G&A overhead costs plus a net profit markup.
- Equipment should be marked up 25 percent for G&A overhead costs plus a net profit markup.
- Subcontractor costs should be marked up 5 percent plus a net profit markup.
- Field labor to include labor burden should be marked up 48 percent for G&A overhead costs plus a net profit markup.
Bill left the workshop as confused as ever. However, he now had the magic numbers to bid his work – at least he thought he did. Unfortunately, he was given faulty mathematical advice that could cause him to overprice or underprice his bids.
How it works in the field.
To illustrate why using percentages to allocate G&A overhead costs to your pricing is inaccurate, we will price three one-month jobs using Bill’s entire labor force. His G&A overhead costs are $10,000 per month and his field labor costs to include labor burden
Analysis.
We kept the cost of field labor and equipment the same for all three jobs as they were one-month jobs requiring the entire field labor force. However, we changed the material costs on each job. Job A had a normal amount of material costs on it and the G&A overhead cost allocated to that job was accurate at just about $10,000. The G&A overhead allocated to Job A was accurate in this case.
However, Job B was a material-intense job and the G&A overhead costs allocated to it were $11,990 or just about $2,000 too high for a one-month job. Job C had no material costs because either the owner bought the materials, or it was a heavy labor job with minimal or no materials. The G&A overhead costs allocated to it were $2,000 too low.
Conclusion.
The primary objective of cost estimating is to calculate your costs accurately whether they be materials, labor and labor burden, equipment, subcontractor costs or G&A overhead costs. Using the MORS estimating method, Bill allocated roughly $2,000 too much G&A overhead on Job B and roughly $2,000 too little G&A overhead costs on Job C. In a competitive market, you’ll usually get the jobs that you underprice and lose the jobs that you
I understand the MORS estimating method pretty well. I taught it to landscape contractors for three years in the late 1980s until I realized how inaccurate it was. I even wrote a book about it, A Critical Analysis of the MORS Estimating System, where I describe how using percentages to mark up direct costs and allocate G&A overhead costs to bids is extremely inaccurate. If you disagree with me, I challenge you to show me mathematically where I am wrong. You may win a lot of work using the MORS estimating method, but I guarantee that you’ll lose this argument with me every time.
Explore the August 2018 Issue
Check out more from this issue and find your next story to read.
Latest from Lawn & Landscape
- LawnPro Partners acquires Ohio's Meehan’s Lawn Service
- Landscape Workshop acquires 2 companies in Florida
- How to use ChatGPT to enhance daily operations
- NCNLA names Oskey as executive vice president
- Wise and willing
- Case provides Metallica's James Hetfield his specially designed CTL
- Lend a hand
- What you missed this week